Alewijnse has completed the electrical installation works for the new Double Joint Factory (DJF) on Allseas’ Solitaire, one of the world’s largest pipelay vessels. The upgraded DJF enhances automation, data integration and operational efficiency in pipelay operations.
As part of the project, Alewijnse was responsible for the complete electrical installation scope, supporting the delivery of a fully renewed DJF that has been central to Solitaire’s pipelay operations for more than 25 years. The company also provided support during engineering, testing and commissioning activities to help ensure successful system integration and start-up.
Also read: Alewijnse lands Port of Rotterdam fleet maintenance
New cable routes and equipment
Key elements of the project included the installation of new cable routes and cable support systems, as well as sensors, junction boxes, control panels and other electrical and instrumentation (E&I) equipment.
Alewijnse also carried out the pulling, termination and connection of all required cables for power, control, instrumentation and network systems. In addition, all cables and components were identified and tested through continuity and insulation resistance testing.
The project involved close collaboration between all parties and a constantly changing schedule. but was completed on schedule nonetheless.
Picture: Alewijnse completed the electrical installation works for the new Double Joint Factory of Allseas‘ Solitaire, one of the world’s largest pipelay vessels (photo Alewijnse).
Also read: Allseas signs first contract for pipelay vessel Solitaire upgrade