Boskalis commissioned a large-scale shore power facility on 14 November at its premises in the Waalhaven in Rotterdam, the Netherlands. Boskalis vessels are (de)mobilised for own projects at this service centre. From now on, the moored vessels will switch off their diesel-powered generators and use green shore power.

In addition, Rotterdam Shore Power’s shore power installation will be used for a variety of land-based electrical equipment deployed by Boskalis to carry out projects in the region.

The shore power installation is expected to generate 2 GWh of green electricity per year, resulting in an annual CO2 reduction of 1600 tonnes. In addition, shore power contributes significantly to improving air quality by reducing particulate matter and nitrogen emissions and contributes positively to the living environment by reducing noise levels.

Also read: Boskalis headed for one of the best years in its history

Reducing the carbon footprint

The new shore power installation is part of a series of measures taken by Boskalis to reduce its carbon footprint and promote the use of renewable energy sources at its offices and service centres. In recent years, for example, many thousands of solar panels have been installed on the roofs of the offices on the Boskalis campus in the Dutch city of Papendrecht and in Singapore and on the roof of the central distribution centre in Vlaardingen, the Netherlands.

Furthermore, a large-scale electric vehicle charging facility was commissioned on the Papendrecht campus; with 252 charging points, one of the largest of its kind in the Benelux region.

Also read: Boskalis and IHC ink deal for 31,000 m3 dredger

Green shore power

Boskalis sources the green shore power from Rotterdam Shore Power (a joint venture between Eneco and the Port of Rotterdam Authority), which owns the shore power installation, with Boskalis having realised the grid connection in-house. The green power supplied by Eneco originates from its Dutch wind and solar sources.

The project was co-financed by the municipality of Rotterdam and the European Union through the European Regional Development Fund.

Also read: Boskalis wins large cable contracts for Baltica 2 offshore wind farm