The Seajacks Leviathan and Seajacks Kraken have been prepared for their coming assignments following a series of repair and renewal jobs by Shipdock Amsterdam.

The shipyard, part of Damen Shiprepair & Conversion, had been commissioned for the two jack-ups by Seajacks UK Ltd.

Great Yarmouth (United Kingdom) based Seajacks has assigned the shipyard various and different major and minor adjustments on the two jack-up sister vessels in between North Sea offshore windfarm and oil & gas installation contracts.

Heli Deck and Below Deck Reinforcements for Leviathan

The Seajacks Leviathan first had its blade racks cut loose and removed after completion of a wind turbine and propeller blade operation. Subsequently, the self-propelled jack-up had a heli deck installed in Shipdock’s 250 m Panamax dock.

This included all related drain and fire fighting piping. The heli deck had been prefabricated by Niron Staal, a Damen Shiprepair subsidiary located at the shipyard’s premises in Amsterdam.

In addition, below deck reinforcements were installed to support the heavier mounts in view of future replacement of the lifeboat davits.

Kraken Replaces Lifeboat Davit Sets

Shipdock Amsterdam’s major work on the Seajacks Kraken involved the replacement of the vessel’s two entire lifeboat davit sets. This included installing Niron Staal prefabricated foundations and the four new davits with their powerpack, cable, winch, electricity and hydraulic systems. This was finished off by surveyor-assessed test runs and loads test.

Furthermore, the Kraken’s four legs were restored after an initial joint inspection round with the principal’s inspectors. Repairs involved S690 grade steel.

In addition to crane tests and crane hook certification update surveys, both Seajacks jack-up vessels underwent miscellaneous minor steel work and had four new satellite dome platforms installed.