On 27 February Van Oord’s Managing Director John van Herwijnen signed the contract for the Maasvlakte 2 port expansion project at Rotterdam. Van Oord has a fifty per cent stake in the PUMA consortium, which will be carrying out phase 1 of the project. The total value of the contract for this phase amounts to more than 1 billion euros.
Van Herwijnen said he is happy that after impressive land reclamation projects elsewhere in the world – for example The Palm and The World in Dubai – the company is now able to show its capabilities in its own country.
The first part of the Maasvlakte 2 site will be constructed between 2008 and 2013. Under the contract, the consortium will construct 11 km of seawall, the first 700 ha or so of the new port site (900 ha in total), and 3 km of quay walls. It will also dig the port basins to their required depth and build 11 km of roads. The contract further stipulates that the consortium will be responsible for maintaining the Maasvlakte 2 seawall for an initial five-year period after the work is completed. The project will require 240 million m³ of sand, 7.5 million tonnes of stone and concrete blocks.
The first container terminal will begin to operate in 2013.
Source: https://www.vanoord.com/webfront/base.asp?pageid=452[VanOord.com]