Costa Crociere and Titan Micoperi have confirmed that sponson installation operations have immediately resumed after receiving authorisation from the Monitoring Observatory. Soon after, however, sponson S13 appeared in need of repairs, causing further delays.

Before problems arose with S13, works were back on track with the installation of the starboard sponson S11, the third of the nineteen to be installed.

Delay with Sponson S13

After installing sponson S13, it showed a disequilibrium. Technicians emptied the sponson of ballast water while the sponson was kept in position with the support of the Conquest crane. The S13 was then loaded on a pontoon and delivered at a shipyard in Genoa for technical assessment and repairs. Repositioning of S13 will therefore be completed at a later stage.

Technicians have also assessed minor damages also in the adjacent sponson (S12), caused by contact with sponson S13 during its rotation. Remediation on this starboard sponson is in progress on site at Giglio island.

Installation of the remaining sponsons has resumed as soon as the Conquest crane became available again. The technicians are currently working on installing sponson S9.