Jan De Nul has launched another next level high-performance vessel: the William Thomson, one of two identical subsea cable laying vessels currently under construction. Both vessels have a cargo capacity of 28,000 tonnes and a length of 215 metres. This makes them the largest of their kind.

Subsea cables are needed to bring energy generated at sea ashore and to connect the electricity grids between different countries and regions. Like its identical sister Fleeming Jenkin, the William Thomson was launched at the CMHI Haimen shipyard in China.

Also read: Jan De Nul orders new vessel to bury energy cables

Laying cables at depths of up to 4000 metres

Jan De Nul’s two new cable-laying vessels have been specially built to install these cables, both in shallow and ultra-deep waters down to 4000 metres. Thanks to their large loading capacity, they can take longer cables on board in a single piece and bridge longer distances with as few subsea cable connections as possible.

Compared to other cable-laying vessels on the market, they therefore also need to make fewer return trips to load cables. This reduces costs, minimises the environmental footprint and enhances cable quality.

Entirely self-designed

Sister vessel Fleeming Jenkin was launched in October 2025 and its delivery is scheduled for the last quarter of 2026. The William Thomson will follow shortly and will be operational in the first half of 2027. Both vessels and the technologies on board have been designed by Jan De Nul’s in-house experts.

Wouter Vermeersch, Director Subsea Cables Offshore Energy at Jan De Nul: ‘The William Thomson and its identical sister, the Fleeming Jenkin, bring together all the expertise in cable installation that we have built up over the past fifteen years. They are the highest-performing and most efficient cable-laying vessels on the market.’

Also read: Jan De Nul launches offshore installation simulator

2800 kilometres of subsea cables for TenneT

Once operational, the Fleeming Jenkin and William Thomson can immediately get to work on their first assignments.

Their first project is the 2GW programme by TenneT, the grid operator for the Netherlands and large parts of Germany. This introduces a new generation of grid connections for offshore wind farms, each capable of transporting up to 2 GW. That is more than double the capacity of current connections, which typically range between 700 and 900 MW, making offshore wind energy more efficient and affordable. By way of comparison, an average nuclear power station typically generates between 1 and 1.6 GW.

For this programme, Fleeming Jenkin and William Thomson will install more than 2800 kilometres of 525-kV DC cables for four different grid connections.

Three AC cables for Princess Elisabeth Island in Belgium

In 2028, Jan De Nul will also deploy one of the new cable-laying vessels to install three 220-kV AC cables that will connect the Princess Elisabeth Island to shore. This energy island, which Jan De Nul is building in a joint venture for grid operator Elia, will bundle the cables from Belgium’s second offshore wind zone (Princess Elisabeth Zone) and enable a stronger interconnection between the North Sea countries.

Also read: VIDEO: World’s first energy island is taking shape

Five more vessels on the way

Jan De Nul is investing heavily in the expansion of its existing subsea cable capacity. In addition to the two vessels for installing these cables, three more vessels will be added to protect them: two trenching support vessels to bury cables in the seabed and a rock installation vessel that protects the cables with a layer of rock.

This means that Jan De Nul has five additional vessels for the installation and protection of subsea cables on the way.

About the William Thomson

William Thomson will be equipped with three cable carousels and a large hold for fibre optic cables, capable of laying up to four cables simultaneously. Two carousels are mounted on deck, with a third below deck. The combined cable-carrying capacity amounts to 28,000 tonnes, which is double the capacity of any other cable-laying vessel currently on the market.

On the aft deck, the vessel is equipped with a chute and a cable-laying wheel. In combination with the tensioners, the chute allows installation of cables in shallow waters, while the wheel makes installation at great depths of up to 4,000 metres more efficient. The tensioners enable the vessel to handle and control cable tensions up to 150 tonnes – the weight of the Statue of Liberty.

Also read: VIDEO: Jan De Nul launches world’s largest cable-layer

Green technologies

The vessel is an ultra-low emission vessel (ULEv). ULEv is a highly advanced dual exhaust filter system which removes up to 99 per cent of nanoparticles from emissions using a diesel particulate filter and a reduction system for nitrogen oxides (NOx). The system also significantly reduces exhaust gas pollutants.

The engines of the vessel can run on biofuel and green methanol, reducing CO2 emissions. Thanks to the ULEv system, the vessel complies with the strict European Stage V emission standards for inland waterway vessels. Moreover, the NOx emissions are reduced to such an extent that this vessel meets the even stricter EURO VI emission limits.

The hybrid power plant on board also contributes to the reduction of CO2 emissions and optimal fuel usage. It combines the generators with a 2.5 MWh battery and drive technology, designed for peak shaving, load smoothing, spinning reserve and optimised engine loading.